The slurry wall is finished and unfastened. More than 50,000 m³ of soil has been completely selected and removed under its protection. We started production of a first level reinforced concrete slab with pits for elevator shafts and other technological equipment.
Reinforcement work is being carried out now. In one of the sections, the slab has already been poured and the columns are ready to cover the second level. Stabs are being prepared for the reliable connection of the floor slab and the wall. Despite the difficulties associated with hot weather, the work is proceeding with a good pace and proper quality. Wait for the next report and visit our Facebook page.