Construction of the Holodomor Victims Memorial National Museum continues. The difficult winter weather conditions have passed and with the onset of spring weather, construction work has been kicked into high gear. A horizontal formwork is now being installed to cover the second floor. In parallel with this, retaining walls , an intermediate exit from the inclined elevator are being erected. Work has begun on the formation of the relief of the slope. At the same time, strict control over the condition of the slope is carried out for its stability.