OSNOVA LLC continues construction of the Holodomor Victims Memorial National Museum. Today we are performing monolithic reinforced concrete vertical structures on the last floor of the building of the new museum. On the pedestrian bridge, trays for green spaces are mounted and a flying slab is equipped. In difficult conditions, work is underway to drill the vertical shaft of the communication manifold. We are renovating the interior and exterior adjoining area of ​​the existing museum. Installation of external engineering networks continues. They brought in black soil, planned out and sowed grass on the slope. On the first floor of the new building, the temporary floor supports were removed - now the work front for masons has opened. Finishing work has begun in the lobby of the inclined elevator; we are laying granite floor slabs.