News from the Holodomor Museum

News from the Holodomor Museum

in August 2023
The construction of the second stage of the Holodomor Museum has moved into the stage of finishing work, the reinforced concrete supporting structures are actually completed. The waterproofing of the coating is completely ready, now gratings are being installed to hold the soil. Painted metalwork. A metal frame for a hinged facade made of granite slabs is being installed. The pedestrian bridge is fully paving, stainless steel railings are being installed and the crossing structures are being sheathed with finishing slabs. The final solutions of the architectural design of this grandiose structure are already being seen.
An interesting report was made by Pavlo Avdokushin. We recommend to see.