Completed works:
— Construction of membrane bioreactor unit;
— Arrangement of production and auxiliary building of treatment facilities;
— Construction of primary settling tank of pumping station, vacuum pump ;
— Power supply;
— External networks of household sewerage;
— External sewerage networks;
— External water supply networks. Wastewater treatment pipelines;
— Access roads;
— Installation of metal structures of building frame — 88 t;
— Construction of foundations — 183 m³;
— Installation of monolithic reinforced concrete structures — 898 m³.