Reconstruction with construction of  Holodomor Victims Memorial Complex
Customer:
State Unitary Enterprise Directorate for construction of the second stage of  National Museum Holodomor Victims Memorial
Years of construction:
2018 - under construction
Completed works: 
—  Earthworks — 39600 m³; 
—  Grillage on retaining walls — 1670 m³; 
—  Preparation period; 
—  Installation of retaining walls PS-1, PS-2, PS-3, PS-4, PS-5, PS-6, PS-7 
—  Installation of bored piles ø 820 mm, ø 1020 mm;
—  Installation of a monolithic wall.